Case Study - Unit Engineers and Constructors

A look into one of our more recent contracts, Unit Engineers and Constructors completed a highly successful contract for a customer.   

Esso Fawley IB2 & MEK 2019 T/A

Key stats-

· Personnel on site from 3Q 2018 to support scope preparation, building to a full Site Team for Execution, Close Out & QA Handover in Q3 & Q4 2019.

· Included Mechanical Support for a minor stage-outage in May 2019, c. 1100hrs.

· Facilitated the order to supply 4 x replacement fin-fan bundles.

· Peak Manning Level - 78, Total Man hours on Project c. 36,000.

· 100+ welds completed – zero repairs required.

IB2 Unit - 66 Work Packages Completed: (Now online – Zero Leaks Reported).

· Replacement of 5 x fin-fan bundles and overhaul of 3 other exchangers.

· 12 Piping Repairs

· 35 Valve replacements

MEK Unit – 45 Work Packages Completed: (Start-Up ongoing – Zero Leaks Reported)

· 9 Exchanger Inspections/Overhauls

· 21 Piping repairs

· 17 valve Replacements

· Repairs carried out to main furnace

With a clean safety record on this contract and over 1 million man hours without a reportable injury, this was a very successful job for Immingham based Unit Engineers and Constructors, with high performing KPIs resulting in total project value being in excess of £2 million.


Navigation

Contact Us

+44 (0) 1792 654 091

  • LinkedIn
  • Twitter
  • Facebook
  • YouTube
  • Instagram

© 2020 UNITBIRWELCO - All Rights Reserved.

A Sustainable Engineering Company.

Unit House, Elba Business Park, Elba

Crescent, Swansea, SA1 8QE